1980 : First 11/4 kV Distribution Transformer
1994 : First 33/11 kV Power Transformer (30 MVA)
2001 : First 132/11 kV Power Transformer (45 MVA)
: First 132/33 kV Power Transformer (90 MVA)

Major Milestone in Transformer Manufactured

Tenaga Nasional Berhad (TNB), Malaysia

8 x 30 MVA 132/11 kV successfully manufactured and put to service since 2001.
More than 250 units of 30 MVA 33/11 kV successfully manufactured and put to service since 1994.

Sabah West Coast Project (SESB), Malaysia

2 x 90 MVA 132/66 kV
4x 45 MVA 132/33 kV
2x 30 MVA 132/11 kV
4x 30 MVA 132/11 kV

Saudi Electricity Company (SEC), Saudi Arabia

1 x 1000 kVA 13.8/0.231 kV
1 x 100 kVA 13.8/0.231 kV

Ceylon Electricity Board, Sri Lanka

2 x 30 MVA 33/11 kV

 

Major Milestone in Project

A joint venture project between Canadian and Malaysian governments on “Malaysia Rural. Electricity Project: Coupling Capacitive System” in the 1980s.

Major Milestone in Services (Repair and Retrofit of Power Transformers)

2001 : 353 MVA 275/20 kV for Kapar Power Station, Klang Malaysia.
: 25 MVA 275/34.5/11 kV for Kapar Power Station, Klang Malaysia
2002 : 250 MVA 275/230/22 kV for Plentong Transmission Main Intake Malaysia
2007 : 240 MVA 275/132/33 kV for PMU Ayer Tawar, Perak Malaysia
2008 : 6 x 90MVA 132/33 kV for various PMU in Malaysia